Bangladesh Goes Nuclear: Rooppur Plant Sends First Power to the Grid

Current Affairs

Why in News? 

On 17 November 2026, Unit 1 of the Rooppur Nuclear Power Plant supplied Bangladesh’s first nuclear electricity to the national grid on a trial basis. 

  • Power fed: 350 MWe at 15:16 local time; the trial connection was planned for 8–10 hours before a pause and reconnection. 
  • Milestone: Science and Technology Minister Fakir Mahbub Anam said Bangladesh is now the 33rd country to generate nuclear power. 
  • Criticality: Unit 1 first reached criticality on 11 October 2026; its operating licence was issued on 16 April 2026. 
  • Next steps: Commercial operation follows a trial period and regulatory approval (reported as early 2027); Unit 2 is expected to start up in 2027. 
  • Share: Once fully operational, the plant should meet over 10% of Bangladesh’s electricity demand. 

Rooppur Nuclear Power Plant 

  • Location: Rooppur, Ishwardi upazila, Pabna district, north-west Bangladesh, about 160 km from Dhaka, on the Padma (Ganga) river. 
  • Design: Two Russian VVER-1200 pressurised water reactors of 1,200 MWe each (2,400 MWe total); water acts as coolant and moderator. 
  • Partner: Built by Russia’s state nuclear corporation Rosatom; general contract of about US$12.65 billion signed in December 2015. 
  • Construction: Unit 1 began November 2017; Unit 2 began July 2018. 
  • Life: 60 years, extendable by 20 years; spent fuel is to be returned to Russia. 
  • India link: In 2018, India, Russia and Bangladesh signed an MoU for cooperation on Rooppur – India’s first trilateral nuclear project in a third country.